高压进撬,稳压出站High pressure in, steady pressure out

CNG 减压撬:槽车 20 MPa 的压缩天然气,在撬上完成换热、两级减压、计量与安全放散,稳到管网或直供用户能用的压力。CNG pressure reducing skid: 20 MPa yard gas is heated, reduced in two stages, metered and relieved on one skid, down to network or burner pressure.

首页Home/产品中心Products/CNG 减压撬CNG pressure reducing skid
CNG 减压撬
01 / Overview

产品概述Product overview

CNG 减压撬解决的问题很具体:槽车压力随存量从 20 MPa 一路衰减到 3 MPa 以下,而下游管网只认 0.2–0.4 MPa(直供工业窑炉可低至 0.09 MPa)。中间这段落差既是压力问题,也是温度问题——高压天然气节流后温度可骤降到 −30℃ 以下,不换热就会结霜、冰堵,甚至冻裂阀口。泰燃的做法是把减压与换热放在同一撬体里成对设计,而不是先减压再补加热。Yard pressure decays from 20 MPa toward 3 MPa while the network only accepts 0.2–0.4 MPa. Joule-Thomson cooling can push gas below −30 °C, so reduction and heat exchange are designed as one pair on a single skid.

典型结构为两级减压串联:一级把 20–25 MPa 降到 2.0–3.0 MPa,二级再降到用户压力。单级压差被拆小,阀口冲刷和噪音随之下降,调节精度也更容易守住。工业和连续供气场合按“一开一备”双路配置,主路检修时备用路自动接替,不停气。换热按现场条件三选一:电加热(无热水源的点供站)、热水(锅炉或余热)、蒸汽(有蒸汽源的工厂)。Two-stage reduction splits the ratio, reducing seat erosion; duty/standby circuits keep gas flowing during maintenance. Heat source is electric, hot water or steam depending on site.

撬体出厂前完成焊接、探伤、强度与气密试验、抛丸涂装,控制柜与仪表接线在厂内联调。到现场只剩基础找平、进出口对接、氮气置换与升压——这也是撬装相对厂站式最大的价值,土建量和工期一起压缩。Welding, NDT, pressure and leak tests, blasting and coating are finished in the workshop; on site only levelling, connection, purging and pressurising remain.

CNG 减压撬
三台撬体同批总装:减压、换热与计量在出厂前逐台做气密和调压标定。Three skids in one batch; every unit gets a leak test and regulator calibration before delivery.
A / Working principle

工作原理:为什么必须“先换热、再减压”Working principle: heat first, reduce second

压缩天然气从槽车出来时是 20 MPa 的高压气体,进入管网前必须降压。降压动作本身是节流——气体通过阀口时不做外功,焓值基本不变,压力降下去、温度也就跟着掉下去。这是焦耳-汤姆逊效应,天然气在常温段的节流温降系数大致在每降 1 MPa 掉 0.4–0.5 ℃ 的量级,从 20 MPa 降到 0.4 MPa 的落差足以把气体拉到零下几十度。CNG leaves the trailer at up to 20 MPa and must be reduced before it enters a network. Throttling keeps enthalpy roughly constant, so the pressure drop becomes a temperature drop. For natural gas near ambient the Joule-Thomson coefficient is in the order of 0.4–0.5 °C per MPa, and a drop from 20 MPa to 0.4 MPa is enough to take the gas tens of degrees below zero.

温度掉下去会带来两个后果:一是水分析出结冰,二是一级阀口的密封材料失去弹性。冰堵不是“偶尔的故障”,而是设计不当的必然结果。所以泰燃的撬体把换热器放在一级减压之前,先把进气加热到有余量的温度,再让它节流;这样二级阀口拿到的始终是不结冰的气体。Two consequences follow: free water freezes, and elastomer seats lose resilience at the first-stage seat. Icing is not an occasional fault — it is the predictable result of a wrong layout. Tairan therefore puts the heat exchanger ahead of the first-stage reducer, so the gas entering the second stage is always above the icing window.

气路顺序固定为:进口球阀 → 过滤器(拦截颗粒与锈渣)→ 换热器 → 一级减压 → 二级减压 → 安全切断/放散 → 计量 → 出口。每一段之间都留取压口,便于现场用压力表分段判断堵塞与泄漏位置;这是后期运维最省事的细节。The gas path is fixed: inlet ball valve → filter → heat exchanger → first-stage reduction → second-stage reduction → safety shut-off / relief → metering → outlet. A pressure tap between every section lets a fitter locate a blockage or leak segment by segment — the cheapest maintenance detail to build in.

02 / Structure

结构组成What is on the skid

01
撬装底座与框架:型钢焊接整体底座。Welded steel skid base.
02
一级减压阀组:高压减压阀配上游切断阀、过滤器,负责 20 MPa 段的压差。First-stage regulator with upstream shut-off and filter.
03
二级减压阀组:低压段调压,出口压力波动控制在用户设定带内。Second-stage regulator holding the outlet band.
04
换热单元:电加热式、热水壳管式或蒸汽式,出气温度按下游防冰堵要求设定。Electric, hot-water or steam heat exchanger.
05
安全系统:安全切断阀、安全放散阀、超压/超温联锁,与可燃气体探测联动。Slam-shut, relief and over-pressure/temperature interlock.
06
计量与仪表:涡轮/罗茨流量计、压力温度变送器、就地压力表与数据采集。Turbine or Roots meter, transmitters and local gauges.
07
控制系统:PLC 柜,具备双路自动切换、远程信号上传与故障报警。PLC cabinet with auto changeover and remote signals.
CNG 减压撬
柜内布置:两级减压串联,换热段与阀组同撬,检修门开在操作侧。Inside the cabinet: two-stage reduction in series, heat exchanger and valve train on one skid, service doors on the operator side.
03 / Advantages

核心优势Why this design

  • 双路自动切换:主路超压、失压或故障时切至备用路,连续供气不中断。Automatic changeover to standby on fault.
  • 两级减压拆压差:单级压比小,阀口寿命长,出口压力不随上游衰减而漂移。Two stages split the ratio for stable outlet.
  • 成套换热:按现场热源配置,出气温度可控,冬季不冰堵。Heat source matched to site; no winter icing.
  • 厂内完成试验:强度、气密、仪表联调在出厂前做完,现场调试时间短。Shop-tested before shipment.
  • 资质齐全:压力管道元件制造许可 TS2713287-2027、GC2 级安装许可 TS3813652-2027。Manufacture licence TS2713287-2027 and GC2 installation licence TS3813652-2027.
Gallery / 产品图片

产品实拍Product photos

CNG 减压撬 · 出厂前实拍 1CNG 减压撬 · 出厂前实拍 2CNG 减压撬 · 出厂前实拍 3

CNG 减压撬 · 出厂前实拍CNG reducing skid — shop-floor photos 点击图片放大查看。 Click to enlarge.

Models / 规格与实拍

按规格挑,点进去看现场实拍Pick a size, see the site photos

同一个型号,照片比文字更能说明做工:撬体骨架、管路走向、阀组排布、接地点和保温层都在里面。选一个规格,进去看它在车间和现场的实拍。Skid frame, piping runs, valve layout and insulation, shown as built.

04 / Specification

技术参数Technical data

参数CNG-300CNG-500CNG-1000CNG-2000CNG-2000CNG-3000CNG-4000CNG-5000
小时最大流量 Nm³/h300500100020002000300040005000
结构形式一用一备一用一备一用一备一用一备一用一备一用一备一用一备一用一备
调压级数二级二级二级二级三级三级三级三级
进水温度 ℃65–8565–8565–8565–8565–8565–8565–8565–85
一 / 二级换热回水温度 ℃60 / 6060 / 6060 / 6060 / 6060 / 6060 / 6060 / 6060 / 60
出口气体温度 ℃10–2010–2010–2010–2010–2010–2010–2010–20
一级调压后压力 MPa0.4–1.40.4–1.40.4–1.40.4–1.41.0–4.01.0–4.03.0–7.53.0–7.5
二级调压后压力 MPa0.1–0.40.1–0.40.1–0.40.1–0.40.1–0.40.1–0.41.0–4.01.0–4.0
三级调压后压力 MPa0.01–0.020.01–0.020.01–0.020.01–0.030.03–0.050.1–0.40.1–0.40.1–0.4
一级放散压力 MPa1.44–1.761.44–1.761.44–1.761.44–1.761.1–4.41.1–4.43.3–7.73.3–7.7
二级放散压力 MPa0.11–0.440.11–0.440.11–0.440.11–0.440.11–0.440.11–0.441.1–4.41.1–4.4
三级放散压力 MPa0.015–0.0250.015–0.0250.015–0.0250.015–0.0350.035–0.0550.11–0.440.11–0.440.11–0.44
进口通径DN25DN25DN25DN25DN40DN50DN50DN50
出口通径DN50DN80DN100DN100DN150DN150DN200DN200
外形尺寸 长×宽×高 m2.5×1.8×23.0×1.8×23.5×2×2.13.8×2×2.13.8×2×2.15.5×2×2.25.5×2×2.26.0×2×2.2
重量 t0.81.01.31.81.82.02.52.8
功率 kW915306060100120150
选配锅炉功率 kW202550100100150200250

二级调压工艺:槽车来气经一级换热、一级调压(1.0–4.0 MPa)→ 二级换热、二级调压(0.1–0.4 MPa)→ 计量、加臭 → 中压管网;三级调压工艺在此基础上再降到 10–30 kPa 后进入低压管网。各级压力、温度、流量与两路切换均由中控台联锁控制。

以上为常规配置参数,取自公司产品画册;流量、介质、进出口压力与接口不同时按工况单独设计,以合同技术文件为准。

B / Selection

选型与计算要点:先算热负荷,再定阀口Selection: size the heat load before the valve

01
先算热负荷 换热量按“流量 × 焓差”估算,而不是按经验配个功率。流量取高峰小时流量(不是平均流量),焓差取进口状态与出口状态之差;算出热量后,再按电加热、热水或蒸汽的传热条件选型。热负荷算小了,冬天必然冰堵;算大了只是多花一点电。Size the heat load first Heat duty comes from flow × enthalpy difference, using the peak hourly flow rather than the average. Only after that is the heat source — electric, hot water or steam — chosen. Undersizing the duty guarantees winter icing; oversizing only costs a little electricity.
02
两级压差要分得匀 从 20 MPa 降到 0.4 MPa 是 50 倍的压力比,一级减压承担的比例越大,阀口流速越高、噪音和冲刷越严重。把比例分成两段(例如先降到 2–3 MPa 再降到用户压力),单级压差被拆小,阀芯寿命和调节精度一起改善。某些小流量点供站也做单级,但必须确认阀口不会长期在高流速下工作。Split the ratio evenly A 50:1 ratio from 20 MPa to 0.4 MPa cannot sit on one seat without noise and erosion. Splitting it into two stages (say 2–3 MPa on the first) keeps seat velocity low and regulation tight. Single-stage designs exist for small point-supply stations, but only where the seat is not continuously at high velocity.
03
按存量校核最低进口 槽车压力随取气衰减,最后阶段可能只剩 3–5 MPa。选型时不能只看 20 MPa 工况,还要确认在低进口压力下仍能满足出口流量——这往往决定了二级阀口的口径,而不是最大流量。Check the end-of-trailer inlet Trailer pressure decays as gas is drawn off, sometimes to 3–5 MPa at the end. The second-stage seat is usually sized by the low-inlet case, not by the maximum flow, so both ends of the envelope must be checked.
04
备用路与切换方式 连续供气场合按一开一备配置,双路之间用切换阀或自动切换装置。切换应做到“先开后关”,避免瞬时断供;这一点在给医院、窑炉、连续生产线供气时是硬要求。Duty and standby Continuous supply uses duty/standby circuits switched make-before-break, so the outlet never sees a zero-flow moment. For hospitals, kilns and continuous lines this is a hard requirement, not a preference.
05
材质与接口 高压段管道通常取 16MnDG 或不锈钢,阀门与法兰按压力等级配套;密封件要能耐低温,不能按常温丁腈橡胶交差。接口规格与法兰标准建议在合同里写死(例如 HG/T 20592 或客户指定),避免到场后改口。Materials and connections High-pressure pipework is usually 16MnDG or stainless, with valves and flanges matched to the rating; seals must be low-temperature rated. Flange standards (HG/T 20592 or as specified) belong in the contract to avoid on-site re-machining.
05 / Duty

适用工况Typical duties

零散气源 CNG 上载国家管网CNG uploading to national grid工业园区点供与窑炉直供Industrial park point supply城镇燃气补充气源与调峰City gas supplement and peak shaving钻井与偏远井口气发电机组供气Wellhead gas for gensets
06 / Comparison

与传统方案的对比Against the conventional approach

比较维度Item厂站式减压Brick-built station泰燃撬装式Ta'ran skid
建设周期Lead time土建+安装,3–6 个月3–6 months厂内预制,现场 3–7 天接入3–7 days on site
压差处理Pressure split单级大压差,阀口冲刷Single large drop两级拆分,阀口寿命长Split across two stages
冬季运行Winter需另设加热,易冰堵Extra heating needed换热随机集成,出气≥5℃Heat integrated, ≥5 °C
检修供气Maintenance停气检修Supply stops双路自动切换不停气Auto changeover
Fit / 适用与边界

适合什么工况,什么情况不适用Where it fits, and where it does not

这套设备适合Best for

  • 撬装成套,现场只需接进出口管路与电源,安装以小时计Skid-mounted; site work is limited to piping and power
  • 双路一备,换路不停气,适合连续生产用户Duty / standby changeover without stopping supply
  • 两级减压分摊压差,阀后压力稳定、波动小Two-stage reduction keeps outlet pressure steady
  • 换热与计量集成在同一撬上,冬季不易冰堵Heating and metering on one skid; less icing in winter

需要提前确认的边界Check before ordering

  • 需要 20 MPa 级槽车或储气瓶组作气源,无气源不能独立供气Needs 20 MPa yard gas or cylinder banks as source
  • 流量超过 3000 Nm³/h 后撬体尺寸与吊装条件要求提高Above 3000 Nm³/h the skid grows and lifting conditions tighten
  • 出口压力低于 0.05 MPa 的超低压场合需另配末级调压Below 0.05 MPa outlet an extra final stage is needed
Configuration / 标准配置

标准配置Standard configuration

进气过滤Inlet filtration双路篮式过滤器,一用一备,可在线切换清洗Twin basket strainers, duty / standby, switchable online
一级减压Primary regulation主调压器 + 备用调压器,阀后超限自动切换Duty and standby regulators with automatic changeover
二级减压Secondary regulation按出口压力分级设置,两级独立可调Two-stage, each independently adjustable
加热防冰堵Heating / hydrate prevention按压降与温降配置电加热或水套换热Electric or water-jacket heating sized on pressure drop
计量Metering涡轮或罗茨流量计 + 流量计算机,带温压补偿Turbine or Roots meter with flow computer and P/T compensation
超压保护Overpressure protection安全切断阀 + 安全放散阀,双级保护Slam-shut valve plus relief valve, two levels of protection
控制柜Control panelPLC + 触摸屏,压力远传、报警与联锁PLC with HMI, pressure transmission, alarms and interlocks
撬体与管路Skid and piping无缝钢管(20# / 16MnDG),整体撬装,试压与气密合格Seamless steel pipe, skid-mounted, pressure and leak tested

以上为常规配置,实际随机组按工况与用户管网条件确定,可按需增减。Standard scope shown; final scope is set by duty and network conditions, and can be adjusted.

Components / 主要零部件

主要零部件Main components

调压器Regulator主备双路,阀后压力可调,是减压撬的核心Duty and standby, adjustable outlet; the core of the skid
过滤器Filter拦截管道杂质,保护调压器阀口与流量计Traps debris; protects regulator seat and meter
安全切断阀Slam-shut valve超压或失压时自动切断气源Cuts supply on over- or under-pressure
安全放散阀Relief valve超压时定量放散,定压可调Set-pressure relief with adjustable opening
球阀Ball valves进出口与旁通,全通径减小压损Full-bore inlet, outlet and bypass
压力表与变送器Gauges and transmitters就地读数与远传信号Local reading and remote signal
流量计Flow meter计量与结算,配流量计算机Metering and custody transfer with flow computer
控制柜Control cabinetPLC、触摸屏、端子与防爆接线PLC, HMI, terminals and Ex-rated wiring
撬座与吊点Skid base型钢焊接底座,四角吊装Welded steel base with lifting points

零部件的品牌与型号按项目技术要求与用户指定品牌确定,页内不限定具体厂家。Brand and model are fixed by project specification and the user's approved vendor list.

C / FAQ

常见问题:现场最常遇到的五个FAQ: the five questions we hear most

冬天出口压力为什么掉得快?Why does outlet pressure sag in winter?

多数是换热余量不足。进口温度低、热负荷没跟上,一级节流后温度降到冰点以下,二级阀口结霜后流量受限。先查换热器出水/出风温度与热负荷,再查二级阀口是否已经结冰。Usually insufficient heat duty: the first-stage outlet falls below freezing and the second-stage seat frosts up. Check the heater outlet temperature and duty first, then whether the second-stage seat is iced.

出口压力波动大,是阀的问题吗?Is the fluctuation a valve problem?

先看上游是否在切换槽车、进口压力是否突变;再看取压点位置是否离阀口太近。取压点过近会让调节器“追着”自己的动作跑,表现为持续摆动。Check whether a trailer change or an inlet step is upstream, then whether the sensing tap sits too close to the seat — a tap that is too close makes the regulator chase its own action.

噪音大怎么办?How is noise reduced?

节流噪音来自高流速。办法有三个:加大单级压差分配的均衡度、在阀后加消音/扩散段、把出口管径放大一号。不要用包隔音棉的办法糊过去,那是掩盖而不是解决。Throttling noise comes from velocity. Balance the stage ratio, add a diffuser downstream, or step the outlet pipe up one size. Wrapping the pipe in insulation only hides the problem.

能直接给车间供气吗?Can it feed a workshop directly?

可以,但要确认末端用气设备的允许压力范围与流量曲线。直供通常出口压力更低(例如 0.09 MPa 级),此时更要注意出口管径与压损。Yes, provided the end users' allowable pressure band and flow curve are known. Direct supply usually runs at a lower outlet pressure, which makes outlet sizing and pressure loss more critical.

验收要准备哪些资料?What paperwork comes with delivery?

随货交付:材质证明、焊接与探伤记录、强度与气密试验报告、特种设备监督检验报告、电气与仪表调试记录、操作维护手册。资料在厂内一次整理齐,现场只做签收。Material certificates, welding and NDT records, strength and tightness test reports, the special-equipment inspection report, electrical and instrument commissioning records and the O&M manual — compiled in the workshop, signed for on site.